Mechanical ventilation with heat recovery

Also see:
2.1

8.3.1Compliance

MVHR design, materials and sitework shall comply with the Technical Requirements, and be installed by competent operatives.

MVHR systems that comply with the guidance in this chapter and are in accordance with the relevant British Standards and building regulations will generally be acceptable.

MVHR systems should be installed by operatives:

  • competent and familiar with the system being installed, and
  • trained in accordance with the BPEC installer scheme, or other suitable scheme acceptable to NHBC.